New MPS Terminal Goes Live

05-07-2019

New MPS Terminal Goes Live

The MPS Project Team handed over the new Tema Port / Terminal 3 to MPS Operations after 2 years and 8 months of physical works.

The facility handed over includes :

  • 3.55 km of breakwater.
  • 6 mil m3 of material dredged.
  •  9.1 mil m3 of material reclaimed.
  •  57 ha of land including all services and plant
  •  4 main buildings (MPS Administrative building , Authorities Building and Workshop)
  • 15 “small” buildings and facilities,
  •  12 MW power station and substations
  • Gates and OCR
  •  4 scanners
  •  1 fuel station
  • 7 Ship to Shore (STS) cranes, 20 electronic Rubber Tyre gantry Cranes (eRTG) and other small equipment.